VTTV – Truck Loading Station

THE CHALLENGES

Our Customers requested a scaffolding to be able to install the pipe work and cables on the top of the structure and at the same time install the pumps under (both operations were to take place at the same time).

We therefore installed a hanging scaffold with a staircase access.

PROJECT DETAILS

Categories:Industrial
Client:Multimarine Biotek JV
Location:Vasilikos, Zygi area, Cyprus
Surface Area:2700 sq.m
Completed:2014